M/WBE Goals & Reporting Responsibilities
The Department's Minority/Women's Business Programs Unit (M/WBE) has established Minority/Women's Business Enterprise and Equal Employment Opportunity goals by contract type and geographic locations. Construction contracts valued at $100,000 or more and service and commodity contracts valued at $25,000 or more are required to demonstrate good faith efforts to meet these goals. Revenue contracts do not require M/WBE goals; however, the appropriate EEO goals are still required.
The M/WBE Unit's conceptual approval is required on all contracts, loans, grants, application processes and projects financially assisted through NYSDEC. Appropriate M/WBE-EEO language and the correct M/WBE-EEO goals for state assistance contracts should be established during the application process approval phase and must be based on the work to be performed in each individual contract. The M/WBE Unit must be afforded the opportunity to review the application processes for State Assistance prior publication or submission to the Office of State Comptroller for approval.
The M/WBE-EEO goals are required to be placed on the entire project cost, not only on the State/Federal assistance being provided. All contracts that are funded with Federal monies are required to have M/WBE-EEO goals regardless of the expected value. The M/WBE-EEO goals are as follows:
| Location/Commodity Group | MBE Goals | |
|---|---|---|
| New York City (Regions 1 & 2) |
Construction | 21.5% |
| Construction Consultant | 21.5% | |
| Commodities | 18.8% | |
| Services / Technologies | 18.8% | |
| Upstate Region (Regions 3 - 9) |
Construction | 6.0% |
| Construction Consultant | 6.0% | |
| Commodities | 8.8% | |
| Services / Technologies | 8.8% |
| Location/Commodity Group | WBE Goals | |
|---|---|---|
| New York City (Regions 1 & 2) |
Construction | 13.7% |
| Construction Consultant | 13.7% | |
| Commodities | 20.5% | |
| Services / Technologies | 20.5% | |
| Upstate Region (Regions 3 - 9) |
Construction | 6.0% |
| Construction Consultant | 6.0% | |
| Commodities | 8.8% | |
| Services / Technologies | 8.8% |
| Location/Commodity Group | EEO Goals |
|---|---|
| EEO Minority Workforce Participation Goals | 10.0% |
| EEO Female Workforce Participation Goals | 10.0% |
M/WBE Reporting Requirements
Once an application is approved, recipients of Federal/State assistance programs are required to implement a comprehensive M/WBE-EEO program and submit and M/WBE-EEO Work Plan (PDF, 1.07 Mb) with supporting documentation, for review and approval by the OMWBP.
For each contract of the project, the designated Minority Business Enterprise Officer is responsible for ensuring that the completed Detailed M/WBE-EEO Utilization Plan (PDF, 919 Kb) from the Prime Contractor is submitted to OMWBP ten days after the awarding of the contract. This form provides the OMWBP information as to who will be working on the project and if the goals assigned are attained.
The OMWBP also requires recipients of Federal/State assistance programs to submit Quarterly Reports (PDF, 1.07 Mb) detailing payments received by the Prime Contractor and payments made out to NYS Certified M/WBEs.
| Contract Number | Contractor Name | Description/ Reason for Waiver |
Start Date | End Date |
|---|---|---|---|---|
| C303423 | Riverhead Foundation | Waiver granted based on contract being a sole source provider completing work with own employees (force account) | 4/01/2007 | 3/31/2012 |
| C303493 | The Nature Conservancy | Waiver granted for highly specialized fire mgmt tasks, restoration and research/ no M/WBE availability. | 4/01/2006 | 3/31/2011 |
| C303408 | City of Rome | Waiver (partial) granted (17,314) based on speciality work. The remainder of 11,000 will be expected to meet goals. | 4/04/2007 | 3/31/2010 |
| C303406 | City of Rome | Waiver (partial) granted (18,910), based on no response to solicitation, and unreasonably high bid from lone response.Remainder of the goals expected to be met (3,250). Also, need ELAP Cert | 4/04/2007 | 3/31/2010 |
| C303404 | City of Rome | Waiver (partial) granted (18,910) based on only one qualified response to the solicitation, bid unreasonably high for contract. Remainder of goals to be met (2,207) ELAP Cert. needed. | 4/04/2007 | 3/31/2010 |
| C303407 | City of Rome | Waiver (partial) granted (23,056) based on only one qualified response to the solicitation, bid unreasonably high for contract. Remainder of goals to be met (2,850) ELAP Cert. needed. | 4/04/2007 | 3/31/2010 |
| C303403 | City of Rome | Waiver (partial) granted (31,840) based on only one qualified response to the solicitation, bid unreasonably high for contract. Remainder of goals to be met (3,500) ELAP Cert. needed. | 4/04/2007 | 3/31/2010 |