Tentative Schedule
Sea Level Rise Task Force Schedule
Schedule Chart in PDF (24 Kb)
| Task | Who | Start | Finish |
|---|---|---|---|
| Appoint SLRTF members | 6/16/08 | 6/24/08 | |
| SLRTF meeting 1 | Lowery | 6/27/08 | 9/27/08 |
| Appoint staff steering committee | Snyder | 6/9/08 | 7/18/08 |
| Develop budget & update framework | Lowery | 6/30/08 | 10/17/08 |
| Identify work group leaders | SSC | 6/30/08 | 8/1/08 |
| Recruit work group members | WG Leaders | 6/30/08 | 9/26/08 |
| Draft SLR assumptions & scope of SLR effects & deliver to SLRTF | Belensz | 8/4/08 | 11/7/08 |
| Draft outreach plan & deliver to SLRTF | Outreach WG | 10/14/08 | 11/7/08 |
| SLRTF meeting 2 | 11/7/08 | 11/7/08 | |
| Review draft SLR assumptions & scope | SLRTF | 11/7/08 | 11/7/08 |
| Review outreach plan | SLRTF | 11/7/08 | 11/7/08 |
| Finalize assumptions of SLR and impact scope | SSC | 11/7/08 | 11/7/08 |
| Finalize outreach plan | Outreach WG | 11/10/08 | 11/13/08 |
| Staff Steering Committee Meeting/Call | 11/24/08 | 11/24/08 | |
| Public Scoping Meetings | 11/17/08 | 2/13/09 | |
| Secure venues | 11/25/08 | 12/8/08 | |
| Prepare agenda, presentations, etc. | 11/17/08 | 11/28/08 | |
| Announce scoping meetings | 12/22/08 | 12/22/08 | |
| Conduct scoping meetings | 1/19/09 | 1/30/09 | |
| Summarize scoping meeting input | 2/2/09 | 2/13/09 | |
| SLRTF meeting 3 | 2/23/09 | 2/23/09 | |
| Review of public comments | SLRTF | 2/23/09 | 2/23/09 |
| Final report | 5/21/09 | 10/28/09 | |
| Draft 1 final report/deliver to SSC | WG Leaders | 5/21/09 | 5/21/09 |
| Review & comment on draft 1 final report | SSC | 5/22/09 | 6/4/09 |
| Draft 1a final report/deliver to SSC | WG Leaders | 6/5/09 | 6/18/09 |
| Draft 1a final report final review/deliver to SLRTF | SSC | 6/19/09 | 7/2/09 |
| Review draft 1 final report | SLRTF | 7/3/09 | 7/16/09 |
| Draft 2: final report | SSC | 7/17/09 | 8/6/09 |
| Release draft 2 final report | Outreach WG | 8/7/09 | 8/7/09 |
| Public review of draft 2 final report | Outreach WG | 8/31/09 | 9/30/09 |
| Draft 3: final report | SSC | 10/1/09 | 10/28/09 |
| SLRTF meeting 4 | SSC,Outreach WG | 11/12/09 | 11/12/09 |
| Review draft 3 final report | SLRTF | 11/12/09 | 11/12/09 |
| Finalize report | SSC | 11/13/09 | 12/10/09 |
| Submit report | SLRTF | 12/10/09 | 12/10/09 |