| Region 5 SEQR and Other Notices | Region 5 SPDES Renewals |
ENB Region 5 Completed Applications 09/27/2006 |
Clinton County |
|
| Applicant: | Noble Altona Windpark LLC 7430 NYS Rte 11 Churubusco, NY 12923 |
|---|---|
| Facility: |
Noble Altona Windpark Multiple Sites Altona, NY 12910 |
| Application ID: | 5-0920-00057/00001 |
| Permit(s) Applied for: |
Article 24 Freshwater Wetlands Section 401 - Clean Water Act Water Quality Certification Article 15 Title 5 Excavation & Fill in Navigable Waters Article 15 Title 5 Stream Disturbance |
| Project is Located: | Altona, Clinton County |
| Project Description: | |
|
Noble AltonaWindpark,
LLC (Noble) is proposing to install and operate a wind-powered
generating facility consisting of 68 wind turbines and associated facilities within an
approximate 4,144-acre area in the Town of Altona, Clinton County, New York.
Each
turbine has a capacity of 1.5 megawatts (MW), and the combined total capacity of the
project is approximately 102 (MW). In addition to the wind turbines, the project will involve
the construction and use of approximately 17.6 miles of access roads, an electrical collection
system, a new substation constructed on a 1.62-acre parcel that will tie into an existing 230-kilovolt
(kV) New York Power Authority (NYPA) Plattsburgh – Willis line to provide access to
the grid, and associated staging areas for parking and storage. The actual project footprint will
occupy approximately 150 acres within the project area.
The
wind turbines to be installed will be General Electric (GE) 1.5 MW wind turbines with
each turbine consisting of a tubular steel tower with a 77-meter-(253-foot)-diameter rotor, and a
nacelle which houses the generator, transformer, and power train. The rotor and nacelle are
mounted on top of the tower giving the rotor hub a height of 262 feet (80 meters). Each turbine
has a maximum height of approximately 389 feet (120 meters) with a rotor blade oriented
straight up, and will occupy a concrete base with a diameter of approximately 18 feet. Aviation
lights will be limited to the minimum required by the Federal Aviation Administration (FAA)
and aviation warning lights will be installed only on structures along the project perimeter.
A
pad transformer will be located adjacent to the base of each tower, raising the voltage of the
electricity produced by the turbine generator up to the 34.5 kV voltage level of the collection
system. The project will include approximately 9.9 miles of trenched-in ground and about 9.9
miles of overhead 34.5 kV electric cable to collect all the power from the turbines and terminate
at the main substation. The new substation will be located on a 1.62 acre parcel approximately
300 feet to the west of the Military Turnpike, and approximately 2,000 feet south of Duley
Road.
Regulated
freshwater wetlands and state-protected streams are located within the project
area, and permits are required for the construction of access roads, the construction of the
turbines, and the buried electric cable interconnection lines. The project as proposed will result
in 0.49 acres of temporary impacts and 0.065 acres of permanent impacts to DEC-jurisdictional
freshwater wetlands, and 5.05 acres of impacts to DEC regulated wetland buffer area. The
project also anticipates 80 linear feet of temporary and 25.56 linear feet of permanent impact to
state-protected streams. The applicant is currently investigating mitigation options with the U.S.
Army Corps of Engineers and the NYSDEC to provide acceptable compensatory mitigation for
the permanent impacts to both federal and state-regulated freshwater wetlands.
|
|
| State Environmental Quality Review (SEQR) Determination: | |
| A draft environmental impact statement has been prepared on this project and is on file. | |
| SEQR Lead Agency: | |
| Altona Town Board | |
| State Historic Preservation Act (SHPA) Determination: | |
| A cultural resources survey has been completed. Based on information provided in the survey report, the New York State Office of Parks, Recreation and Historic Preservation (OPRHP) has determined that the proposed activity will have an impact on registered or eligible archaeological sites or historic structures. The department must consult further with OPRHP before making a final decision regarding the issuance of the permit. | |
| Coastal Management: | |
| This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act. | |
| Opportunity for Public Comment: | |
| Comments on this project must be submitted in writing to the Contact Person no later than Oct 12 2006. | |
| Contact: | Stephen M Tomasik NYSDEC Headquarters 625 Broadway Albany, NY 12233 (518)402-9167 depprmt@gw.dec.state.ny.us |
| Region 5 SEQR and Other Notices | Region 5 SPDES Renewals |