| Region 5 SEQR and Other Notices | Region 5 SPDES Renewals |
ENB Region 5 Completed Applications 10/26/2005 |
Essex County |
|
| Applicant: | International Paper Co International Paper Plaza 400 Atlantic St Stamford, CT 06921 |
|---|---|
| Facility: |
International Paper Ticonderoga Mill 568 Shore Airport Rd Ticonderoga, NY 12883 |
| Application ID: | 5-1548-00008/00081 |
| Permit(s) Applied for: |
Article 19 Air Title V Facility |
| Project is Located: | Ticonderoga, Essex County |
| Project Description: | |
|
This is a Supplement
to the Notice of Complete Application published in the October 12,
2005 ENB. The applicant, International Paper Company (IP) has applied for a
modification of its Air Pollution Control Title V Permit to conduct a two week trial burn
to evaluate the use of tire derived fuel as an alternate fuel source for the mill’s power
boiler. The Department has prepared a Draft Permit and has made a tentative
determination to approve this application for modification. This modification would
authorize a two week trial and testing period during which tire-derived fuel (TDF) will be
combusted in the power boiler along with number 6 fuel oil and bark/wood. The TDF
loading will not exceed 3 tons per hour and the total heat input to the boiler will not
exceed 748 MMBtu per hour. TDF will be added to bark/wood in the wood yard and be
conveyed with the bark/wood to the boiler. During the first week, TDF will be added in
gradually increasing amounts while the boiler operators adjust the boiler to achieve
optimum combustion conditions. Particulate Matter emissions will be measured (using
USEPA Method 5) when the TDF feed rate reaches 1 ton per hour, then again at 2 tons
per hour and again at 3 tons per hour to ensure compliance with the permit limit during
this period. During the second week, extensive stack testing will be performed to
characterize emissions.
Whenever TDF is being
burned, facility personnel will monitor the SO2 emission rate
and NOX emission rate utilizing the mill’s continuous emissions monitoring systems.
Stack opacity will be monitored by certified personnel during daylight hours. If any of
these indicators exceed permit limits, the facility will stop adding TDF until the
conditions have stabilized and are in compliance.
In accordance with 6NYCRR
Parts 621.5(d)(9) and 2016.4(c), the Administrator of the
United States Environmental Protection Agency (USEPA) has the authority to bar
issuance of any Title V Facility Permit if it is determined not to be in compliance with
applicable requirements of the Clean Air Act or 6NYCRR Part 201.
Legislative Public Hearing sessions have been scheduled. For details on date, time and place for the hearing proceedings and procedures for participation, please refer to the following web site link: http://www.dec.state.ny.us/website/ohms/notices/international2.html A copy of the Department's permit hearing procedures is available upon request or on the Department's web site at: www.dec.state.ny.us/website/ohms/gudph1.htm |
|
| State Environmental Quality Review (SEQR) Determination: | |
| Project is not subject to SEQR because it is a Type II action. | |
| SEQR Lead Agency: | |
| None Designated | |
| State Historic Preservation Act (SHPA) Determination: | |
| The proposed activity is not subject to review in accordance with SHPA. The permit type is exempt or the activity is being reviewed in accordance with federal historic preservation regulations. | |
| Coastal Management: | |
| This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act. | |
| Opportunity for Public Comment: | |
| Comments on this project must be submitted in writing to the Contact Person no later than Dec 9 2005. | |
| Contact: | Michael J McMurray NYSDEC Region 5 Headquarters 1115 NYS Rt 86 Ray Brook, NY 12977 (518)897-1234 r5dep@gw.dec.state.ny.us |