| Region 5 SEQR and Other Notices | Region 5 SPDES Renewals |
ENB Region 5 Completed Applications 02/05/2003 |
Essex County |
|
| Applicant: | Jay - T PO Box 730 Au Sable Forks, NY 12912 -0730 |
|---|---|
| Facility: |
Straight Pit Valley Rd Ausable Forks, NY 12912 |
| Application ID: | 5-1528-00002/00001 |
| Permit(s) Applied for: |
Article 23 Title 27 Mined Land Reclamation |
| Project is Located: | Jay, Essex County |
| Project Description: | |
|
The applicant proposes expanding
the existing sand and gravel pit by .85 acres to the
north, for a total Life of Mine boundary of 8.0 acres. The site, owned by Benjamin
Straight, is located .4 mile south of the Valley Road and Straight Road intersection.
|
|
| State Environmental Quality Review (SEQR) Determination: | |
| Project is an Unlisted Action and will not have a significant impact on the environment. A Negative Declaration is on file. A coordinated review was not performed. | |
| SEQR Lead Agency: | |
| None Designated | State Historic Preservation Act (SHPA) Determination: |
| Cultural resource lists and map have been checked. No registered, eligible or inventoried archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required. | |
| Coastal Management: | |
| This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act. | |
| Opportunity for Public Comment: | |
| Comments on this project must be submitted in writing to the Contact Person no later than Mar 7 2003. | |
| Contact: | Denise M Wagner NYSDEC Region 5 Headquarters Rt 86 Ray Brook, NY 12977 (518)897-1234 dmwagner@gw.dec.state.ny.us |
Franklin County |
|
| Applicant: | Malone - V 14 Elm St Malone, NY 12953 -1507 |
| Facility: |
Malone - V WWTP Lane St Malone, NY 12953 |
| Application ID: | 5-1648-00013/00004 |
| Permit(s) Applied for: |
Article 17 Titles 7 & 8 Municipal SPDES |
| Project is Located: | Malone, Franklin County |
| Project Description: | |
|
The applicant has an existing
State Pollutant Discharge Elimination System (SPDES)
permit authorizing the discharge of 3.3 million gallons per day (MGD) of treated sanitary
wastewater to the Salmon River, and 1.76 MGD to groundwater via infiltration basins,
from a municipal secondary wastewater treatment plant located at Lane Street, in the
Village of Malone. The applicant requests a modification to the permit to delete the
action level limit for phenols, delete the infiltration & inflow program, delete the mini
pre-treatment program, and delete the monitoring requirements for totat kjeldahl nitrogen.
And, the Department is initiating a modification to the permit to increase the sampling
requirements for effluent nitrate for outfall 002 from 1 grab sample per month to 1 grab
sample per week.
The Department has made
a tentative determination to modify the SPDES permit under
Article 17 of the Environmental Conservation Law. This tentative determination
indicates that the discharge rgulated under this statute is considered to satisfy regulatory
standards for permit issuance, based on information available to the Deparmtent at this
time. As a tentatvie determination, the Department seeks comments on the proposed
modifications prior to making a final decision. As such, this tentative determination does
not signify Department approval for or endorsement of the actifity for which the
modification is sought.
|
|
| State Environmental Quality Review (SEQR) Determination: | |
| Project is an Unlisted Action and will not have a significant impact on the environment. A Negative Declaration is on file. A coordinated review was not performed. | |
| SEQR Lead Agency: | |
| None Designated | State Historic Preservation Act (SHPA) Determination: |
| The proposed activity is not subject to review in accordance with SHPA. The permit type is exempt or the activity is being reviewed in accordance with federal historic preservation regulations. | |
| Coastal Management: | |
| This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act. | |
| Opportunity for Public Comment: | |
| Comments on this project must be submitted in writing to the Contact Person no later than Apr 7 2003. | |
| Contact: | Denise M Wagner NYSDEC Region 5 Headquarters Rt 86 Ray Brook, NY 12977 (518)897-1234 dmwagner@gw.dec.state.ny.us |