| Region 2 SEQR and Other Notices | Region 2 SPDES Renewals |
| Kings County | ||
| Applicant: | Kings Harbor View 163 Degraw Street Brooklyn, NY 11231-3006 |
|
| Facility: |
Kings Harbor View-Van Brunt To Pier 41 Van Brunt St To Pier 41 Brooklyn, NY - |
|
| Application ID: | 2-6102-00219/00001 | |
| Permit(s) Applied for: |
Article 25 Tidal Wetlands Section 401 - Clean Water Act Water Quality Certification Article 15 Title 5 Excavation & Fill in Navigable Waters |
|
| Project is Located: | Brooklyn, Kings County | |
|
Project Description: The applicant proposes the reconstruction and restoration of the Red Hook waterfront from the Beard Street warehouse to to Pier 41. The work includes repair of a boat launch ramp at the north end of Beard Street, construct of a boardwalk and placement of rip-rap south of Pier 41, placement of rip-rap southwest of the boardwalk and at the head of Pier 44, construction of a 200 foot by 12 foot pier in the location of the remains of former Pier 44, installation of a bulkhead at the end of Conover Street, placement of rip-rap and construction of a 25 foot pier; 30 foot ramp and 10 foot by 60 foot floating dock between Conover Street and Van Brunt Streets and placement of rip-rap along the north side of Beard Street Pier with new steel sheeting along the seaward edge of the pier. |
||
| State Environmental Quality Review (SEQR) Determination: Project is not subject to SEQR because it is a Type II action. | ||
| SEQR Lead Agency: None Designated | State Historic Preservation Act (SHPA) Determination: Cultural resource lists and map have been checked. No registered, eligible or inventoried archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required. | |
| Coastal Management: This project is located in a Coastal Management area and is subject to the Waterfront Revitalization and Coastal Resources Act. | ||
| Opportunity for Public Comment: Comments on this project must be submitted in writing to the Contact Person no later than Oct 12 2001. | ||
| Contact: | Harold J. Dickey NYSDEC Region 2 Headquarters 47-40 21St Street Long Island City, NY 11101 (718)482-4997 hjdickey@gw.dec.state.ny.us |
|
| Richmond County | ||
| Applicant: | NYC Dept Of Sanitation 125 Worth St New York, NY 10013-4006 |
|
| Facility: |
Staten Island Transfer Station Fresh Kills Staten Island, NY 10314- |
|
| Application ID: | 2-6403-00141/00001 | |
| Permit(s) Applied for: |
Article 25 Tidal Wetlands Article 19 Air State Facility Article 27 Title 7 Solid Waste Management |
|
| Project is Located: | Staten Island, Richmond County | |
|
Project Description: The applicant proposes to construct and operate a new truck-to-rail solid waste transfer station which will receive and process for export municipal solid waste generated on Staten Island. The transfer station will have a design throughput capacity of 2,880 tons per day; the estimated average throughput will be 1,150 to 1,200 tons per day. The facility will cover an approximately twenty-acre site currently used for administrative and other non-landfilling functions at the Fresh Kills Landfill, located north of Fresh Kills Creek and west of the West Shore Expressway. All solid waste transfer activities will take place within a fully-enclosed, 70,000 square foot building. A 3,300-foot rail spur will be constructed to connect the facility to the end of the existing Travis branch of the Staten Island Railroad. The spur will cross tidal wetlands north of Little Fresh Kills and east of the Arthur Kill. Stormwater outfall contruction will additionally affect tidal wetlands along Fresh Kills Creek. The applicant will mitigate for wetland habitat losses by creating and restoring additional tidal wetland areas in the vicinity of the facility site at a ratio of no less than 3 times the wetland area lost or disturbed. |
||
| State Environmental Quality Review (SEQR) Determination: A final enviromental impact statement has been prepared on this project and is on file. | ||
| SEQR Lead Agency: NYC Dept of Sanitation | State Historic Preservation Act (SHPA) Determination: A cultural resources survey has been completed. The report of the survey is on file. No archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required. | |
| Coastal Management: This project is located in a Coastal Management area and is subject to the Waterfront Revitalization and Coastal Resources Act. | ||
| Opportunity for Public Comment: Comments on this project must be submitted in writing to the Contact Person no later than Oct 12 2001. | ||
| Contact: | John F. Cryan NYSDEC Region 2 Headquarters 47-40 21St Street Long Island City, NY 11101 (718)482-4997 jfcryan@gw.dec.state.ny.us |
|