ENB Region 1 Completed Applications 06/28/00

Nassau County
 
Applicant: Concord Term.corp.d/b/a Carbo Concord
One Bay Blvd.
Lawrence, NY 11559-1104
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: Marilyn E. Peterson
SEQR: Project is not subject to SEQR review because it is a Type II action.
SHPA: Cultural resource lists and map have been checked. No registered, eligible or inventoried archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required
Last Filing Date: 07/21/2000
Project Location: Hempstead
Project Description:
Amended Notice due to typo which appeared in 6/21/00 ENB project description:The Department has drafted a permit pursuant to Article 19 (Air Pollution Control) of the NYS Environmental Conservation Law (ECL) and Title V of the Federal Clean Air Act Amendments, and made a tentative determination to approve this application for the existing gasoline and distillate oil storage and distribution terminal, located at 1 Bay Blvd. Lawrence, NY 11559. This facility consists of 8 permitted gasoline bulk storage tanks and 5 storage tanks for gasoline additives. There is one tank truck loading rack at the site. Gasoline vapor emissions are controlled with a vapor reduction unit. Emissions from this facility are controlled in accordance with multiple State and Federal regulations. The applicant has accepted throughput limitations for gasoline and distillate oil and will keep records of hazardous air pollutant emissions to prove that facility emissions remain below the applicability level of the National Emission standards for gasoline distribution facilities. Draft permit and application are available at Region 1 office. In accordance with 6NYCRR Part 621.6(d)(9), the administrator of the USEPA has the authority to bar issuance of any Title V facility permit, if it is to be determined not to be in compliancewith requirements of the Clean Air Act or 6NYCRR Part 201.
Permit: Article 19: Title V Facility Permit
Permit ID:DEC-1-2820-01085/00006

 
Applicant: Commander Oil Corp
1 Commander Square
Oyster bay, NY 11771-1536
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: Marilyn E. Peterson
SEQR: Project is an unlisted action and will not have a significant effect on the environment. A Negative Declaration is on file. No coordinated review was performed.
SHPA: Cultural resource lists and map have been checked. No registered, eligible or inventoried archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required
Last Filing Date: 07/21/2000
Project Location: Oyster Bay
Project Description:
Amended Notice due to typo which appeared in ENB project description on 6/21/00. The Department has drafted a permit pursuant to Article 19 (Air Pollution Control) of the NYS Environmental Conservation Law (ECL) and Title V of the Federal Clean Air Act Amendments, and made a tentative determination to approve the application for the existing gasoline and distillate oil storage and distribution terminal, located at 1 Commander Sq., Oyster Bay, NY. This facility consists of 7 permitted gasoline bulk storage tanks and 11 storage tanks,for gasoline additives, heating oil diesel oil. There are 2 tank truck loading racks. Gasoline vapor emissions are controlled with a vapor reduction unit. Emissions from this facility are controlled in accordance with multiple State and Federal regulations. The applicant has accepted throughput limitations for gasoline and distillate oil and will keep records of hazardous air pollutant emissions to prove that facility emissions remain below applicable level of the National emission standards for gasoline distribution facilities. A draft permit and application are available at the Region 1 office. In accordance with 6 NYCRR Part 621.6(d)(9) the administrator of the USEPA has the authority to bar issuance of any Title V facility permit if it is to be determined not to be in compliance with the applicable requirements of the Clean Air Act or 6NYCRR Part 201.
Permit: Article 19: Title V Facility Permit
Permit ID:DEC-1-2824-00455/00010

Suffolk County
 
Applicant: New York Power Authority
1633 Broadway
New york, NY 10019-6708
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: Carol A. Farkas
SEQR: Project is an unlisted action and will not have a significant effect on the environment. A Negative Declaration is on file. No coordinated review was performed.
SHPA: The proposed activity is not subject to review in accordance with SHPA. The permit type is exempt or the activity is being reviewed in accordance with federal historic preservation regulations.
Last Filing Date: 08/04/2000
Project Location: Brookhaven
Project Description:
The Department has drafted a permit pursuant to Article 19 (Air Pollution Control) of the NYS Environmental Conservation Law and made a tentative determination to approve this application for the applicant's facility located at 607 Union Ave, Holtsville, NY. Richard M. Flynn Power Plant has one Siemens turbine rate at 1146 BTU/hr when firing natural gas and 1291 mmBTY/hr when firing No. 2 fuel oil (back up fuel). The combined cycle (gas turbine and steam turbine) generates 150 MW of power for sale to Long Island Power Authority. The control equipment includes Dry Low NOx Combustor within the turbine in combination with water injection to reduce NOx and CO2 emissions. The Title V permit requires continuous emission monitoring of NOx and CO, wet and dry O2 emissions. VOCs and particulates emissions will be monitored upon request by the Department. Fuel consumption and water injection rates will be monitored on a continuous basis as well. Fuel Sulfur will be monitored in the fuel oil on a per delivery basis. The sulfur content in the fuel shall not exceed 0.020% by weight in the fueil oil. the facility has a heat recovery steam generator which uses the exhaust from the gas turbine to generate steam which in turn generate more electricity using a steam turbine. The Title V permit contains a complete listing of the applicable Federal, State and compliance monitoring requirements for the facility. The facility is also subject to the Title IV requirements as per 40 CFR Part 73 and 76. Although there is no SO2 allowances for the facility, a total of 200 allowances were transferred from the Charles Poletti Power Station to this facility as of August 22, 1994. In accordance with 6NYCRR Parts 621 (d)(9) and 201-6.4(c), the Administrator of the US Environmental Protection Agency (USEPA) has the authority to bar issuance of any Title V facility permit if it determined not to be in compliance with applicable requirements of the Clean Air Act or 6NYCRR Part 201. The draft permit is available for inspection and comments at the Region 1 office in Stony Brook.
Permit: Article 19: Title IV (Phase II Acid Rain)
Article 19: Title V Facility Permit
Permit ID:DEC-1-4722-00926/00006

 
Applicant: Martin Atkin
31 West 12th St - Apt 2e
New york, NY 10011
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: Claire K. Werner
SEQR: Project is not subject to SEQR review because it is a Type II action.
SHPA: Cultural resource lists and map have been checked. No registered, eligible or inventoried archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required
Last Filing Date: 07/14/2000
Project Location: East Hampton
Project Description:
The applicant proposes to reconstruct 126 feet of bulkhead in-place, and excavate 38 cubic yards of material from behind 52 feet of bulkhead, which will be removed. Fifty-two feet of new bulkhead will be constructed landward of old bulkhead. The applicant also proposes to install 50 to 100 lb stone adjacent to 41 feet of bulkhead, and place 38 cubic yards of fill behind the bulkhead. The bulkhead replacement will result in the elimination of an approximate 300 square foot area of tidal wetlands known as intertidal marsh. The applicant proposes to plant a 1750 square foot area with native species. The project is located at 73 Louse Point Road, East Hampton, Town of East Hampton, Suffolk County, SCTM# 300-83-3-10.2 &11.
Permit: Article 25: Tidal Wetlands
Permit ID:DEC-1-4724-00915/00001

 
Applicant: Patricia C. Remmer
500 Shore Rd
Oakdale, NY 11769
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: John A. Wieland
SEQR: Project is a Type I action and will not have a significant effect on the environment. A Negative Declaration is on file and a coordinated review with other agencies has been performed.
SHPA: A Structural-Archaeological Assessment Form has been completed. The proposed activity will not have any impact on registered, eligible or inventoried archaeological sites or historic structures. No further review in accordance with SHPA is required.
Last Filing Date: 07/14/2000
Project Location: Islip
Project Description:
The applicant proposes to subdivide a 12.5 acre parcel into 8 lots allowing for single family dwelling development and installation of a septic system on each lot. The project is known as the Fisherman's Cove Subdivision proposal located east & west of Shore Drive, 569' south of Oceanview Ave., extending south & east to The Grand Canal, Oakdale, (SCTM # 0500-402-2-1.2).
Permit: Article 25: Tidal Wetlands
Permit ID:DEC-1-4728-02461/00001

 
Applicant: Brian Balodis
343 East 30th St
New york, NY 10016
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: Marilyn E. Peterson
SEQR: Project is not subject to SEQR review because it is a Type II action.
SHPA: Cultural resource lists and map have been checked. No registered, eligible or inventoried archaeological sites or historic structures were identified at the project location. No further review in accordance with SHPA is required
Last Filing Date: 07/14/2000
Project Location: Southampton
Project Description:
APPLICANT PROPOSES TO CONSTRUCT A SECOND STORY ADDITION TO AN EXISTING SINGLE FAMILY DWELLING WHICH IS LOCATED 8 FEET FROM THE TIDAL WETLAND BOUNDARY. AN SECOND ADDITION MEASURING 22' X 28' LOCATED TO THE SOUTH AND PLACED 45' FROM THE WETLAND BOUNDARY WILL BE ADDED TO THE EXISTING DWELLING. THE PROJECT IS LOCATED ON 1323 MEADOW AVENUE, SOUTHAMPTON, VILLAGE OF SOUTHAMPTON.E
Permit: Article 25: Tidal Wetlands
Permit ID:DEC-1-4736-05395/00001

 
Applicant: William Baylis
2200 Wantagh Ave
Wantagh, NY 11793
Office: NYS DEC
Building 40
SUNY Campus
Stony Brook, NY 11794
(516) 444-0365
Contact: Margaret M. Rorke
SEQR: Project is an unlisted action and will not have a significant effect on the environment. A Negative Declaration is on file. No coordinated review was performed.
SHPA: A Structural-Archaeological Assessment Form has been completed. The proposed activity will not have any impact on registered, eligible or inventoried archaeological sites or historic structures. No further review in accordance with SHPA is required.
Last Filing Date: 07/21/2000
Project Location: Southold
Project Description:
applicant proposes to construct a 65' low-sill bulkhead with a 7' southern return and a 12' northern return and backfill with approximately 50 cy of clean sand. Backfill area will be planted with Spartina alterniflora. Existing fixed dock to be removed and replaced with a 4' x 16' catwalk elevated a minimum of four feet above grade over the marsh, a 3' x 14' ramp and a 6' x 20' float. the ramp and float will be removed and replaced seasonally. existing piles will be removed. the project is located at arshamomaque ave, town of southold on pettys pond. sctm #1000-66-3-1.
Permit: Article 25: Tidal Wetlands
Section 401 - Clean Water Act: Water Quality Certification
Article 15, Title 5: Excavation & Fill in Navigable Waters
Permit ID:DEC-1-4738-02469/00001