ENB Region 5 Completed Applications 12/07/2016

Essex County

Applicant:

LC Camp LLC
20 Montchanin Rd Ste 250
Wilmington, DE 19807

Facility:

Camp Woodsmoke Boathouse
Hansen Property Lot 331 Parcel I
Lake Placid, NY 12946

Application ID:

5-1544-00014/00006

Permit(s) Applied for:

Article 15 Title 5 Docks, Platforms & Moorings
Section 401 - Clean Water Act Water Quality Certification

Project is Located:

St Armand, Essex County

Project Description:

The applicant proposes to construct a 9-slip boathouse and a 5-slip boathouse, for a total of 14 slips (7,656 sq/ft), at the site of the former Camp Woodsmoke (Echo Bay) on Lake Placid. A permit was issued in 2010 to replace an existing 6-slip boathouse/docking facility (1,702 sq/ft) with a 9-slip boathouse (5,582 sq/ft), but construction was not completed. The facility is for private use.

Availability of Application Documents:

Filed application documents, and Department draft permits where applicable, are available for inspection during normal business hours at the address of the contact person. To ensure timely service at the time of inspection, it is recommended that an appointment be made with the contact person.

State Environmental Quality Review (SEQR) Determination:

Project is an Unlisted Action and will not have a significant impact on the environment. A Negative Declaration is on file. A coordinated review was not performed.

SEQR Lead Agency: None Designated

State Historic Preservation Act (SHPA) Determination:

Evaluation using a Structural-Archaeological Assessment Form or other information has concluded that the proposed activity will not impact registered, eligible or inventoried archaeological sites or historic structures.

Coastal Management:

This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act.

DEC Commissioner Policy 29, Environmental Justice and Permitting (CP-29)

It has been determined that the proposed action is not subject to CP-29.

Opportunity for Public Comment:

Comments on this project must be submitted in writing to the Contact Person no later than Dec 22, 2016.

Contact:

Rebecca A Smith
NYSDEC Region 5 Headquarters
1115 St Rte 86
Ray Brook, NY 12977
(518)897-1234
DEP.R5@dec.ny.gov


Saratoga County

Applicant:

Peckham Materials Corp
20 Haarlem Ave
White Plains, NY 10603 -2223

Facility:

Peckham Materials Plant 44
Coy Rd
Greenfield Center, NY 12833

Application ID:

5-4134-00006/00015

Permit(s) Applied for:

Article 15 Title 15 Water Withdrawal Non-public

Project is Located:

Greenfield, Saratoga County

Project Description:

The applicant has applied for an initial permit for the continued withdrawal of 700 gallons per minute of water from an on-site pond for the purpose of aggregate production. The facility has been in operation since 2000. No changes in current operations from recent years are proposed.

The Department has determined that the Facility is eligible for an Initial Permit under Section 15-1501.9 of the Environmental Conservation Law. Initial Permits are limited to existing facilities for existing water withdrawals over 100,000 gallons per day which were properly reported to the Department prior to February 15, 2012. Section 15-501.9 requires the Department to issue Initial Water Withdrawal Permits for the reported volume.

The Department has determined that the issuance of "initial permits" under ECL section 15-501.9 as implemented by 6 NYCRR 601.7 is a ministerial action and therefore subject to the Type II exemption set out in 6 NYCRR 617.5(c)(19).

Availability of Application Documents:

Filed application documents, and Department draft permits where applicable, are available for inspection during normal business hours at the address of the contact person. To ensure timely service at the time of inspection, it is recommended that an appointment be made with the contact person.

State Environmental Quality Review (SEQR) Determination:

Project is not subject to SEQR because it is a Type II action.

SEQR Lead Agency: None Designated

State Historic Preservation Act (SHPA) Determination:

The proposed activity is not subject to review in accordance with SHPA. The application type is exempt and/or the project involves the continuation of an existing operational activity.

Coastal Management:

This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act.

DEC Commissioner Policy 29, Environmental Justice and Permitting (CP-29)

It has been determined that the proposed action is not subject to CP-29.

Opportunity for Public Comment:

Comments on this project must be submitted in writing to the Contact Person no later than Dec 22, 2016.

Contact:

Karyn Hanson
NYSDEC Headquarters
625 Broadway
Albany, NY 12233
(518)402-9167
DEPPermitting@dec.ny.gov


Warren County

Applicant:

Peckham Materials Corp
20 Haarlem Ave
White Plains, NY 10603 -2223

Facility:

Peckham Chestertown Plt
Rt 9
Chestertown, NY 12817

Application ID:

5-5224-00010/00015

Permit(s) Applied for:

Article 15 Title 15 Water Withdrawal Non-public

Project is Located:

Chester, Warren County

Project Description:

The applicant has applied for an initial permit for the continued withdrawal of 1,100 gallons per minute of water from an on-site pond for the purpose of aggregate production. The facility has been in operation since 1956. No changes in current operations from recent years are proposed.

The Department has determined that the Facility is eligible for an Initial Permit under Section 15-1501.9 of the Environmental Conservation Law. Initial Permits are limited to existing facilities for existing water withdrawals over 100,000 gallons per day which were properly reported to the Department prior to February 15, 2012. Section 15-501.9 requires the Department to issue Initial Water Withdrawal Permits for the reported volume.

The Department has determined that the issuance of "initial permits" under ECL section 15-501.9 as implemented by 6 NYCRR 601.7 is a ministerial action and therefore subject to the Type II exemption set out in 6 NYCRR 617.5(c)(19).

Availability of Application Documents:

Filed application documents, and Department draft permits where applicable, are available for inspection during normal business hours at the address of the contact person. To ensure timely service at the time of inspection, it is recommended that an appointment be made with the contact person.

State Environmental Quality Review (SEQR) Determination:

Project is not subject to SEQR because it is a Type II action.

SEQR Lead Agency: None Designated

State Historic Preservation Act (SHPA) Determination:

The proposed activity is not subject to review in accordance with SHPA. The application type is exempt and/or the project involves the continuation of an existing operational activity.

Coastal Management:

This project is not located in a Coastal Management area and is not subject to the Waterfront Revitalization and Coastal Resources Act.

DEC Commissioner Policy 29, Environmental Justice and Permitting (CP-29)

It has been determined that the proposed action is not subject to CP-29.

Opportunity for Public Comment:

Comments on this project must be submitted in writing to the Contact Person no later than Dec 22, 2016.

Contact:

Karyn Hanson
NYSDEC Headquarters
625 Broadway
Albany, NY 12233
(518)402-9167
DEPPermitting@dec.ny.gov


  • Contact for this Page
  • ENB
    NYS DEC
    Division of Environmental Permits
    625 Broadway, 4th Floor
    Albany, NY 12233-1750
    518-402-9167
    Send us an email
  • This Page Covers
  • Page applies to all NYS regions