LCP OU-1 Final Cover Construction Design Report

This Draft 100% Design Report presents design analysis, plans, and specifications for the LCP OU-1 final cover area construction. The final cover construction includes installation of a low permeability geomembrane barrier to minimize infiltration, construction of a permanent stormwater drainage system designed to increase flows to Wetland A, and restoration as a native grass and wildflower meadow. Other future potential site uses are possible based on the closure design.

The design elements presented in this Draft 100% Design Report for LCP OU-1 final cover area construction include:

  • Drawings for construction of the final cover system
  • Specifications for construction of the final cover system
  • Drawings and specifications for the management of stormwater from the completed
    cover; and
  • Requirements for management of the site during the construction of the final cover system

Construction of the final cover system is expected to occur in the second half of 2014 after completion of the Ninemile Creek removals.

LCP OU-1 Final Cover Design Report- March 2014 (PDF) 1.3 mB, 18 pages

Appendices are at the repositories.


  • PDF Help
  • For help with PDFs on this page, please call 315-426-7403.
  • Contact for this Page
  • Division of Environmental Remediation
    625 Broadway
    Albany, NY 12233
    315-426-7403
    Send us an email
  • This Page Covers
  • Page applies to Region 7